Almonty Korea Tungsten, 19 March 2020 – Pilot plant starts full throttled continued operation producing concentrate.
We’re pleased to announce throughput is being achieved. Fine-tuning and calibration is now underway towards achieving the required WO3 grade and recovery targets.
Crushing unit capable of crushing 1 ton+ of ore per hour
Ball mill optimized for desired particle size and density
Ball mill optimized for desired particle size and density
Scheelite rougher – 2-stage flotation of scheelite with a scavenging cell
Scheelite cleaning unit – 3-stage cleaning for grade concentration
Scheelite cleaning unit – 3-stage cleaning for grade concentration